We realised this harbour layout from design to installation under our own management. In calculating the ramps, we had to take into account the sometimes large difference between high and low water levels. Another challenge was the approach load.
Project details
Client
Ploegvaart B.V.
Location
Lobith
Object
Installation of overnight mooring / facility jetty
Our effort
production scaffolding of approx. 100 x 12 metres, including a 50-metre-long vehicle bridge
production 4 jetties, approx. 35 metres long, including 4 floats with a width of 6 metres